London Stadium (formerly and also known as Olympic Stadium and the Stadium at Queen Elizabeth Olympic Park) is a multi-purpose outdoor stadium at Queen Elizabeth Olympic Park in the Stratford district of London. It is located in the Lower Lea Valley, 6 mi east of central London. +more
Land preparation for the stadium began in mid-2007, with the construction officially starting on 22 May 2008. The stadium held its first public event in March 2012, serving as the finish line for a celebrity run organised by the National Lottery. +more
The stadium hosted the 2017 IAAF World Championships and 2017 World Para Athletics Championships (the first time both events were held in the same location in the same year). It hosts a round of the IAAF Diamond League each year, known as the London Grand Prix, sometimes called the London Anniversary Games. +more
Design and construction
Olympic design
Design brief
During London's bid for the games, promotional materials featured a main stadium with a roof "designed to wrap itself around the venue like muscles supporting the body"; however, at that time there had been no formal design brief agreed. While the bidding process was ongoing, West Ham had talks with the ODA about contributing to the development of a multi-purpose stadium, should London win the bid. +more
On 13 October 2006, the London Organising Committee of the Olympic and Paralympic Games (LOCOG) confirmed that it had selected Sir Robert McAlpine and Populous with whom to start exclusive negotiations to fulfil the eventual design-and-build contract of the new Olympic Stadium after no other organisations met the bidding criteria. The stadium design was launched on 7 November 2007.
Original structure details
Construction of the stadium commenced three months early in May 2008, after the bowl of the structure had been excavated and the area cleared. The building of the stadium was completed in March 2011 reportedly on time and under budget, with the athletics track laid in October 2011.
The stadium's track-and-field arena is excavated out of the soft clay found on the site, around which is permanent seating for 25,000, built using concrete "rakers". The natural slope of the land is incorporated into the design, with warm-up and changing areas dug into a semi-basement position at the lower end. +more
The stadium is made up of different tiers; during the Games, the stadium was able to hold 80,000 spectators. The base tier, which allows for 25,000 seats, is a sunken elliptical bowl that is made up of low-carbon-dioxide concrete; this contains 40 per cent less embodied carbon than conventional concrete. +more
A wrap, funded by Dow Chemical Company to be able to advertise on it until 26 June 2012, covered the exterior during the Olympics. The wrap was made from polyester and polyethene and printed using UV curable inks. +more
To allow for fast on-site assembly, compression truss and roof column connections were bolted; this enabled easy disassembling of the roof structure after the closing ceremonies. The cable-supported roof structure covers approximately two-thirds of the stadium's seating. +more
Stadium interior
The stadium was equipped with a nine lane Mondo 400 m athletics track. The turf in the stadium was grown in Scunthorpe and was a mix of perennial ryegrass, smooth stalk meadow grass, and fescue grass seeds. +more
The stadium's 80,000 seats had a black-and-white 'fragment' theme that matched the overall branding design used by LOCOG for London 2012. The lines all centred on the finish line on the track. +more
Playing surface
The red Mondo 400 m athletics track used for the London 2012 games was laid in August 2011, possessed nine lanes, and was 14 mm thick. It used two vulcanised rubber layers, one of which was a cushioning underside with elongated diamond-shaped cells, which allowed them to flex in any direction. +more
Response
Initially, the stadium design received a mixed response from the media, with reviews ranging from "magnificent" to the derisory "bowl of blancmange". The design was promoted as an example of "sustainable development", but some architecture critics have questioned both its aesthetic value and suitability as a national icon - especially when compared with Beijing National Stadium. +more
Amanda Baillieu writing in Building Design challenged the designer's claims that the stadium is environmentally sustainable and good value for money. Instead, it is asserted that the reality will be the opposite. +more
Stadium island
The stadium site is on former industrial land between the River Lea (which rejoins the Navigation below Old Ford Lock), the City Mill River, and the Old Pudding Mill River, parts of the Bow Back Rivers. Another branch of this system, St Thomas' Creek, 200 m to the south, completes an "island" surrounded by water. +more
Post-Olympic redevelopment
Dennis Hone, chief executive of the LLDC, revealed in November 2012 that the stadium would not meet its reopening deadline of 2014. Instead, it would reopen in August 2015 and retain a capacity of around 50,000 for athletic events. +more
Balfour Beatty were initially contracted to construct the new roof for £41 million; in January 2014 they were awarded a £154 million tender, which includes the earlier contract for the roof, to complete the stadium's transformation works. Imtech G&H were awarded a £25 million contract to carry out electrical and plumbing work. +more
Work commenced on 13 August 2013 with the removal of 25,000 seats and the grass from the field of play. The athletics track was covered with a 75 cm layer of recycled concrete to protect it during the heavy lifting. +more
The black-and-white seating design from the Olympics was replaced with a white, blue and claret design. The new design includes West Ham's name on the East Kop Stand and symbolic crossed hammers on all lower-tier stands, and the retention of the 2012 shard design on the upper tier, albeit in new colouring to match the stadium's anchor tenant. +more
Community track
Following the demolition of the 2012 warm-up track and to comply with IAAF rules requiring one at Construction Category 1 facilities, a new six-lane community track (eight-lane on the straights) has been created immediately adjacent to the south of the stadium. Since 2017, the track is home to Newham and Essex Beagles Athletic Club and is open for around 250days of the year. +more
History
London 2012
The Olympic Stadium hosted its first public event on 31 March 2012, serving as the finish line for the National Lottery Olympic Park Run. Five thousand participants (including celebrities, British athletes and members of the public who won a lottery draw) took part in a 5 mi run around Olympic Park. +more
The stadium hosted both the opening and closing ceremonies at the 2012 Olympic Games. During the Athletics events of the Olympic Games, David Rudisha broke his own world record for the 800 metres to become the first man to run the distance in under 1 minute 41 seconds. +more
The stadium also hosted both the opening and closing ceremonies of the 2012 Paralympic Games. Over the course of the Paralympic Games athletics events, world records were set on the track by; Oxana Boturchuk Martina Caironi, Chen Junfei, El Amin Chentouf, China, Libby Clegg, Arnu Fourie, Marie-Amelie le Fur, Terezinha Guilhermina, Mahmoud Khaldi, Samwel Mushai Kimani, Walid Ktila. +more
In the field events, world records were set by Hani Alnakhli, Alexey Ashapatov, Aigars Apinis Lahouari Bahlaz, Mohamed Berrahal, Kelly Cartwright, Yanlong Fu, Leonardo Diaz, Zeljko Dimitrijevic, Tanja Dragic, Najat El Garraa, Javad Hardani, Todd Hodgetts, Jun Wang, Maroua Ibrahmi, Juan Yao, Mohsen Kaedi, Mohammad Khalvandi, Gocha Khugaev, Karolina Kucharczyk, Assunta Legnante, Maciej Lepiato, Liu Fuliang, Drazenko Mitrovic, Azeddine Nouiri, Katarzyna Piekart, Mariia Pomazan, Nikita Prokhorov, Qing Wu, Markus Rehm, Raoua Tlili, Wang Yanzhang, Zhu Pengkai, and Oksana Zubkovska. Multiple records were set in the field by Dong Xia, Birgit Kober, Na Mi, Yang Liwan, and Wang Zhiming.
Bidding and award for post-Olympics use
The decision on how to use the stadium after the Olympics went through two rounds of bidding: the first was rejected on 11 October 2011, after concerns had emerged about European Union competition law and particularly the risk of illegal state aid.
First tenancy process
The Olympic Park Legacy Company (OPLC) set five criteria: that the new tenant should produce a viable long-term solution that provided value for money, secure a partner with the expertise to operate a legacy solution, reopen the stadium as quickly as possible, allow flexible usage, and make the stadium a distinctive physical symbol that supported regeneration. After receiving and pre-screening over 100 expressions of interest, the formal bidding process of selecting the post-Olympics user of the stadium opened on 18 August 2010. +more
On 12 November 2010, it was announced that two bids had been shortlisted for the stadium post-Olympics. They were a joint bid from +more
Bids
The legacy plan for the stadium had involved converting it into a 25,000- to 30,000-seat athletics stadium with a sports training, science and medicine centre after the 2012 Paralympics. Media reports, however, suggested that several potential tenants were interested in moving to the stadium after the games. +more
Decision, review, and cancellation
On 11 February 2011, the Olympic Park Legacy Company (OPLC) unanimously selected +more
Second tenancy process
Once the original deal collapsed a new process to select a tenant was begun. The athletics legacy clause was clarified to ensure that a track remained in the stadium. +more
In February 2012, 16 parties were interested in the stadium. In July 2012, four bidders were announced: * West Ham United * Intelligent Transport Services, in conjunction with Formula One. +more
In April 2012, the Olympic Park Legacy Company was dismantled, and responsibilities transferred to the newly constituted London Legacy Development Corporation (LLDC). Daniel Moylan, chairman of the LLDC, was removed by Mayor Boris Johnson on 12 September 2012, after having made changes to the leadership of the organisation that annoyed some Board members. +more
In December 2012, West Ham were named as the preferred bidder for the stadium with a separate operator co-ordinating community and sporting use, as well as concerts and events. Leyton Orient's bid was rejected due to its commercial viability and the bid from Intelligent Transport Services, in conjunction with Formula One, was rejected for having too much speculation and uncertainty in their business plan. +more
On 6 March, Barry Hearn of Leyton Orient stated that he would mount another legal challenge as he believed the rules set out by the LLDC had not been followed. Hearn also said he felt Leyton Orient's proposed ground share had been ignored and not properly explored. +more
Supporters of various rival clubs pressed for an inquiry into the LLDC's granting of West Ham's tenancy, arguing that West Ham were being given an unfair advantage by the arrangement. However, in September 2015 the government rejected holding such an inquiry. +more
In September 2018, Lyn Garner, chief executive of the London Legacy Development Corporation, revealed that the £2. 5m paid per year by West Ham did not even cover the cost of staging matches leading to increased debts in running the stadium for the 97-year remainder of their tenancy agreement. +more
Stadium operator
In October 2014, The Evening Standard reported that French company Vinci SA were favourites to be given a contract to run the stadium for ten years. The company which already operates several other stadiums, including the Stade de France in Paris, had reportedly beaten off competition from other companies including Anschutz Entertainment Group who run The O2. +more
Important
Sports
Although West Ham United are the primary tenants, the stadium's operators arrange many other events to take place there.
Athletics
Anniversary Games
On 24 January 2013, it was confirmed that the London Athletics Grand Prix, a Diamond League event, would be switched to the stadium. In February 2013, it was announced that it would also hold a Paralympic athletics event on 28 July. +more
The London Grand Prix was scheduled to move permanently to the stadium in 2016. However, due to the 2015 Rugby World Cup taking place in the stadium, using the original seating configuration, the opportunity came to move the Grand Prix to the stadium a year early, again under the name of the Anniversary Games. +more
The Muller Anniversary Games, the fourth-anniversary event, took place in the stadium on 22-23 July 2016. The IPC Grand Prix events were incorporated alongside Diamond League events on the second day of the meet. +more
The 2017 Muller Anniversary Games was shortened to a one-day event on Sunday 9 July 2017. Its move to an earlier time of the month was due to the 2017 World Athletics Championships
The 2018 edition returned to a two-day event on its typical weekend of 21-22 July. Tom Bosworth set a world record in the 3000 metres walk. +more
The 2019 event was held on 20-21 July.
The 2020 event was scheduled to take place earlier on the 4-5 July. However, the event was cancelled due to the COVID-19 pandemic.
The 2021 event, scheduled to be reduced to a single day and take place on 13 July was not held at the stadium. No event was held in 2022 either due to the UEFA Women's Euro 2022 and the Commonwealth Games.
After a three-year hiatus, the event would return to the London Stadium as a single day event on 23 July 2023.
2017 World Athletics and World Para Athletics Championships
London had bid to host the 2015 World Athletics Championships using the Olympic Stadium. It went up against Beijing's Olympic Stadium and the Polish city of Chorzów. +more
The World Para Athletics Championships were held between 14 and 23 July 2017, with 800,000 tickets available across 16 sessions. The IAAF World Championships followed between 4-13 August 2017 with 700,000 tickets available. +more
2018 Athletics World Cup
In February 2018, London Stadium was announced as the venue for the inaugural Athletics World Cup. The event was held on 14 and 15 July.
Football
The opening game for West Ham was a Europa League match against NK Domžale on 4 August 2016, which West Ham won 3-0 with the stadium sold out, albeit with a reduced capacity of 54,000 as conversion works were still being finished. The official opening match was a friendly with +more
The 2021-22 National League play-off final between +more
Crowd control
At the beginning of the 2016-17 season, West Ham's games were marred by instances of crowd trouble. In a match against Bournemouth on 21 August, some fans arrived with tickets for seats that did not exist. +more
In March 2018, there were protests against West Ham United owner, David Sullivan at the stadium during a 3-0 home defeat to +more
Other sports
Cricket
In May 2014 it was announced that Essex County Cricket Club had agreed to a deal "in principle" to play their Twenty20 cricket matches at the stadium. The venue was also touted as a possible venue for the 2019 Cricket World Cup. +more
Baseball
On 8 May 2018, Major League Baseball announced a two-year deal to host a series of baseball games at the London Stadium in 2019 and 2020. The Boston Red Sox and New York Yankees (a major rivalry in the American League) played a two-game series at the stadium from 29 to 30 June 2019, branded as the 2019 MLB London Series. +more
Prior to the 2019 games, it was announced that the Chicago Cubs and St. +more
Motorsport
In November 2015 the stadium hosted the 2015 Race of Champions event. It was the first occasion since 2008 that Great Britain hosted the event, with Wembley Stadium last staging the contest in 2008. +more
Rugby league
The first rugby league match at the stadium was played between England and New Zealand on 7 November 2015, it was the second test of a three-test series between the sides. The venue also hosted the match between England and Australia as part of the 2016 Rugby League Four Nations. +more
Test# | Date | Team 1 | Score | Team 2 | Attendance | Notes |
---|---|---|---|---|---|---|
1 | 7 November 2015 | 2-9 | 44,393 | 2015 Baskerville Shield | ||
2 | 13 November 2016 | 18-36 | 35,569 | 2016 Four Nations |
Concerts
Since opening in 2016 the stadium has hosted a number of concerts, with Australian rock band AC/DC playing the first concert on the venue after the Olympic Games.
Access
Rail The stadium is located in the south of Queen Elizabeth Olympic Park. Stratford and Stratford International railway stations are the main stations nearest to the Olympic Park and are roughly a 20-minute walk to the stadium. +more
Stations nearby:
Service | Station(s) | Lines |
---|---|---|
London Overground | Hackney Wick Stratford | North London Line |
Docklands Light Railway | Pudding Mill Lane Stratford Stratford International | Lewisham/Canary Wharf-Stratford Stratford International-Beckton/Woolwich Arsenal |
London Underground | Stratford | |
National Rail | Stratford | Great Eastern Main Line West Anglia Main Line Lea Valley Lines |
National Rail | Stratford International | High Speed 1 |
Elizabeth line | Stratford | Elizabeth line |
Road Travellers by car are advised to use the public car parks at Westfield Stratford City, Stratford International station, and the Stratford Centre. The Queen Elizabeth Olympic Park also has several docking stations for the London Cycle Hire scheme.
Bus and coach The following routes serve the London Stadium directly:
Route | Start | End | Areas |
---|---|---|---|
108 | Lewisham station | Stratford International station | East London, South-East London, South London |
308 | Wanstead | Clapton | East London |
339 | Shadwell station | Leytonstone station | East London, North-East London |
388 | Elephant & Castle | Stratford City bus station | Central London, East London, South London |
A further 17 services use Stratford bus station and Stratford City bus station, which offer a network of services across East London. In addition, route 25 from City Thameslink serves Central London.
National Express coach services to Stratford bus station provide a direct connection to Stansted Airport and several other routes to Essex and East Anglia.
2012 establishments in England
Venues of the 2012 Summer Olympics
Athletics venues in London
Football venues in London
Rugby union stadiums in London
Rugby league stadiums in London
Music venues in London
Sports venues in London
Premier League venues
Sports venues completed in 2012
Buildings and structures in the London Borough of Newham
Athletics (track and field) venues in England
Olympic athletics venues
Rugby World Cup stadiums
Sport in the London Borough of Newham
Tourist attractions in the London Borough of Newham
West Ham United F.C.
Queen Elizabeth Olympic Park
2012 Summer Paralympic venues
Populous (company) buildings
Major League Baseball venues
Latest activity









